Dubai, UAE  ·  Residential MEP subcontracting  ·  Prequalification pack sent within 24 hours +971 0 000 0000  ·  WhatsApp the estimation desk
Flux Grid Electromechanical L.L.C Send your BOQ
Electrical · HVAC · Plumbing · Firefighting · ELV

Your handover date is set by the MEP works.

Flux Grid runs the electromechanical package on residential buildings across the UAE. We sequence to your slab cycle, carry the authority approvals ourselves and hand over with the documentation complete.

5 daysMobilised after LOI
48 hrsFirst fix cleared before pour
Day 0As builts and O&M at handover
12 monthsDLP cover, 24 hour response
01 / The problem

Residential jobs rarely slip on structure. They slip on services.

Four failures account for most of the delay a main contractor absorbs on a G+ residential tower, and every one of them lands on the MEP subcontractor.

Costs 2 to 6 weeks

Approvals left to the end

DEWA energisation and the Civil Defence NOC are treated as closeout paperwork. The building is finished and the completion certificate still waits.

Costs 10 to 15 days a floor

Uncoordinated services

Ducting, trays and drainage clash above the false ceiling. The consultant rejects shop drawings twice and the ceiling closes late.

Costs the slab cycle

Crews pulled to another site

Sleeves and conduits are not ready before the pour. The concrete team waits, or worse, pours and you break it open later as a variation.

Costs your retention

Documentation that arrives late

As builts, test records and O&M manuals turn up months after handover. Retention stays locked and every DLP snag comes back to you.

02 / The programme

Eight stages. A written commitment at each one.

Select a stage to see the delay it normally causes and what Flux Grid holds itself to instead.

What usually happens

Mobilisation

The subcontractor is awarded and then goes quiet. Site staff arrive weeks later, builder's work drawings and sleeve locations follow after that, and the first pour is already at risk.

Typical exposure: 2 to 3 weeks before any productive work
What Flux Grid commits to

On site in five working days

A named site engineer, foreman and first crew mobilise within five working days of the LOI. You receive a stage wise mobilisation plan with headcount by trade against your master programme.

Named team · Headcount by trade · Plan issued before start
03 / Scope of works

One subcontractor for the full electromechanical package.

Split packages mean split accountability. When ducting blames electrical and electrical blames plumbing, the delay is yours. We take the whole package on residential buildings.

S.01

Electrical systems

LV distribution from the substation to the last socket, sized and installed to DEWA, ADDC, SEWA or FEWA requirements depending on the emirate.

  • Main and sub main distribution
  • DBs and panels
  • Containment and wiring
  • Lighting and small power
  • Earthing and lightning protection
  • Load testing
S.02

HVAC and ventilation

Split, ducted split and VRF systems for apartments, with the ventilation and exhaust that a residential block actually needs to pass inspection.

  • Split and VRF installation
  • Ductwork and insulation
  • Car park and toilet exhaust
  • Kitchen extract
  • Staircase pressurisation
  • Testing and balancing
S.03

Plumbing and drainage

Potable water, drainage and pumping from the tank room upward, laid out so risers and inverts are fixed before the structure closes on them.

  • Water supply and risers
  • Soil, waste and vent
  • Storm water
  • Booster and sump pumps
  • Water tanks and calorifiers
  • Pressure testing
S.04

Firefighting and fire alarm

Sprinklers, wet risers, detection and the Civil Defence submission that goes with them. The approval is our responsibility, not a document we ask you to chase.

  • Sprinkler networks
  • Wet riser and hose reels
  • Fire pumps
  • Addressable fire alarm
  • Emergency lighting
  • Civil Defence NOC
S.05

ELV and low current

The systems residents notice on day one and complain about first. Installed and commissioned with the main package rather than bolted on afterwards.

  • CCTV
  • Access control
  • Video intercom
  • MATV and satellite
  • Data and telecom
  • Gate barriers
S.06

Commissioning, handover and DLP

Testing recorded as the work proceeds instead of reconstructed at the end, and a maintenance contract available the moment the defects period starts.

  • System testing and TAB
  • Authority inspections
  • As built drawings
  • O&M manuals
  • Snagging and closeout
  • Annual maintenance
04 / How we work

Four things we put in the subcontract, not just the pitch.

C.01

Your crew stays your crew

Manpower is committed by name and headcount for the duration. If we cannot hold the number, you are told in the weekly report before it affects the programme, not after.

C.02

Approvals desk from day one

A dedicated coordinator handles DEWA, ADDC, Civil Defence and Municipality submissions in parallel with construction. You get a live approval tracker every week.

C.03

Priced from the drawings

We quote from the tender drawings and specification with our assumptions written down. Where the drawings are unclear we ask before award instead of claiming after it.

C.04

Documentation as we build

Test records, material approvals and as built markups are filed at each stage. The handover pack is complete on the day of handover because it was never left to the end.

C.05

One weekly report

Progress against the baseline, manpower deployed, approvals status, material deliveries and the risks for the coming fortnight. One page, every Thursday.

C.06

HSE that survives an audit

Method statements and risk assessments submitted before each activity, toolbox talks recorded, and our operatives carry valid third party certification for lifting and hot works.

05 / Prequalification

Everything your procurement team asks for, on one page.

You should not have to email us to find out whether we can be prequalified. The details are here, and the full pack with certificates, insurance schedules and a completed project list is one click away.

Download prequalification pack Request a site visit

Figures shown are placeholders for the mockup. Replace with Flux Grid's actual licence number, authority classification, insurance limits and manpower strength before launch. Do not publish a claim you cannot evidence at prequalification stage.

Legal entityFlux Grid Electromechanical L.L.C
Trade licenceDED Dubai — No. 000000
Licensed activitiesElectromechanical equipment installation and maintenance
Electrical authority enlistmentDEWA Grade 0 · ADDC registered
Civil Defence approvalApproved contractor — firefighting and alarm
Quality and safetyISO 9001 · ISO 45001 · ISO 14001
Insurance in forceThird party liability AED 0,000,000 · Workmen's compensation
Direct manpower000 operatives · 00 engineers
Emirates coveredDubai · Sharjah · Ajman · Abu Dhabi
Typical contract valueAED 0.0m to AED 00m per building
Bank and trade referencesAvailable in the prequalification pack
06 / Delivered

Buildings handed over, with the numbers that matter.

Scope, value, floor count and programme. A main contractor can judge relevance from these four figures faster than from any photograph.

Project photograph

G+12 residential tower

Client
Main contractor
Scope
Full MEP package
Value
AED 0.0m
Programme
00 months, on time
Project photograph

Residential compound, 24 villas

Client
Civil contractor
Scope
Electrical, plumbing, HVAC
Value
AED 0.0m
Programme
00 months, on time
Project photograph

G+4 apartment building

Client
Developer direct
Scope
MEP and firefighting
Value
AED 0.0m
Programme
00 months, on time
07 / Estimation desk

Send the BOQ. You get a price in five working days.

Attach the tender drawings and specification. If anything in them is ambiguous we will come back with questions before we price, so the number you receive is the number you can hold us to.

Estimation
tenders@fluxgrid.ae
Telephone and WhatsApp
+971 0 000 0000
Office
Dubai, United Arab Emirates